ENVIRONMENTAL ASSESSMENT: SUBSIDIARY LEGISLATION

INDEX TO SUBSIDIARY LEGISLATION

Environmental Assessment (Establishment of Appeals Committee) Order

Environmental Assessment Regulations

ENVIRONMENTAL ASSESSMENT REGULATIONS

(section 73)

(29th June, 2012)

ARRANGEMENT OF REGULATIONS

    REGULATION

PART I
Preliminary

    1.    Citation

    2.    Interpretation

    3.    Activities to which Act applies

PART II
Project Brief, Terms of Reference, etc

    4.    Project brief

    5.    Environmental management plan

    5A.    Waste management and rehabilitation plan

    6.    Scoping exercise and report

    7.    Terms of reference

    8.    Environmental impact statement

    9.    Public hearing

PART III
Registration and Certification of Practitioners

    10.    Application for registration

    11.    Certificate of practice

    12.    Register for practitioners

PART IV
General

    13.    Compliance with Code of Conduct

    14.    Restoration into register

        SCHEDULES

S.I. 58, 2012,
S.I. 30, 2021,
S.I. 49, 2021.

PART I
Preliminary (regs 1-3)

1.    Citation

    These Regulations may be cited as the Environmental Assessment Regulations.

2.    Interpretation

    In these Regulations, unless the context otherwise requires “mass media” includes publicly exhibited posters, newspapers, radio, television or other electronic media used for public communication.

3.    Activities to which Act applies

    Subject to section 3 of the Act, activities, locations, thresholds and criteria to which the Act applies shall be as set out in Schedule 1 to these Regulations.

PART II
Project Brief, Terms of Reference, etc (regs 4-9)

4.    Project brief

    An application for a project brief referred to in section 6(2) of the Act shall be in accordance with Form A set out in Schedule 2 to these Regulations, and shall be accompanied by a fee specified in Schedule 3 to these Regulations.

5.    Environmental management plan

    The environmental management plan referred to in section 6(5)(c) of the Act shall be in accordance with Form B set out in Schedule 2 to these Regulations.

5A.    Waste management and rehabilitation plan

    The waste management plan and rehabilitation plan provided for in section 6(5)(b) of the Act shall be in Form C1 set out in Schedule 2.

6.    Scoping exercise and report

    The scoping exercise provided in sections 6(10)(a), 7(1) and 8A(1) of the Act shall be in Form C set out in Schedule 2.

7.    Terms of reference

    The terms of reference referred to in section 8(2) of the Act shall be in accordance with Form D set out in Schedule 2 to these Regulations.

8.    Environmental impact statement

    The environmental impact statement referred to in section 9 of the Act shall be in accordance with Form E set out in Schedule 2 to the Regulations.

9.    Public hearing

    (1) The competent authority shall, in conducting a public hearing referred to in section 11 of the Act, invite comments from the public.

    (2) The public hearing shall be conducted by a presiding officer who shall be appointed by the competent authority.

    (3) The public hearing shall be convened at a venue which is convenient and accessible to persons who are likely to be specifically affected by the proposed activity.

    (4) The date and venue of the public hearing shall be advertised through the mass media for public attention.

    (5) The presiding officer may disallow frivolous and vexatious submissions likely to lead to abuse of the public hearing.

    (6) A person applying for authorisation to undertake an activity whose application is the subject of a public hearing shall be given an opportunity to respond to any submission made at the public hearing and to provide further information relating to the activity.

    (7) Upon conclusion of the public hearing, the presiding officer shall compile a report of the public hearing and submit the report to the competent authority within 10 working days from the date of the public hearing.

PART III
Registration and Certification of Practitioners (regs 10-12)

10.    Application for registration

    (1) An application for registration as a practitioner shall be in Form A set out in Schedule 4 to these Regulations.

    (2) A person who applies to be registered as a practitioner in accordance with these Regulations shall comply with the qualification requirements and certification criteria in Form B set out in Schedule 4 to these Regulations.

    (3) An application under this regulation shall be accompanied by a registration fee as specified in Form C set out in Schedule 4 to these Regulations.

11.    Certificate of practice

    A certificate of practice referred to in section 40 of the Act shall be in accordance with Form D set out in Schedule 4 to these Regulations and shall be issued subject to payment of a fee specified in Form C set out in Schedule 4 to these Regulations.

12.    Register for practitioners

    A register for practitioners kept by the Board referred to in section 38 of the Act shall be in accordance with Form E set out in Schedule 4 to these Regulations.

PART IV
General (regs 13-14)

13.    Compliance with Code of Conduct

    (1) A practitioner registered under these Regulations shall comply with the Code of Conduct of Practitioners in Form F set out in Schedule 4 to these Regulations.

    (2) The Board may suspend the registration of a practitioner who fails to comply with the Code of Conduct.

14.    Restoration into register

    A practitioner whose name has been removed from the register, who wishes to have his or her name restored into the register, may apply to the Board in writing, to be restored into the register.

SCHEDULE 1

(reg. 3)

Activities that require Strategic Environmental Assessment

    (a)    District land use and structural plans;

    (b)    National policies, legislation and development strategies and programmes.

Activities that require a Statement

Projects

EMP

EIA

Environmentally Sensitive Areas

Any development in national parks, game reserves, wildlife management areas, wetlands, within 0.5 km of open surface water, flood plains, important breeding areas for fauna, within 1 kilometre of important archaeological, historical, religious or cultural sites, areas protected under legislation, hilly areas and areas containing rare or endangered flora and fauna

 

all projects

Transboundary Projects

Projects that have transboundary impacts such as fences, bridges, water transfer schemes and power plants and power lines

Power lines outside urban areas or industrial complexes with a voltage of more than 132kV and less than 230kV or less than 15km in length
rehabilitation, reconstruction, or modernisation of the transboundary power lines projects

Power lines outside urban areas or industrial complexes with a voltage of 230kV and above or more than 15km

Extractive and Associated Industry

a.    Prospecting and exploration for oil, coal bed methane, and natural gas, heavy metals and radioactive minerals

when prospecting and exploration is on a freehold land

when prospecting and exploration is on tribal or state land

b.    Operations for the extraction of pit sand, gravel and clay

when extraction is on a freehold land or from an existing burrow pits

all new activities where extraction is on tribal or state land

c.    Mining within a river system or wetland regardless of the size of the mining project

 

all projects

d.    Exploration of minerals where geothermal drilling and blasting is involved

when exploration is on a freehold land

when exploration is on tribal or state land

e.    Exploitation of minerals, including quarrying

 

all projects

f.    Extraction and processing of hydrocarbons including coal

 

all projects

g.    Mineral processing

processing plants with capacity of less than 500,000 tonnes per year

non-metallic mineral processing (crushing, grinding, milling or separation) when production capacity is less than 10,000 tonnes per year

processing plants with capacity of more than 500,000 tonnes per year

non-metallic mineral processing (crushing, grinding, milling or separation) when production capacity is more than 10,000 tonnes per year

h.    Metallurgical and chemical plants associated with mining, including cement and lime kilns manufacturing

installations with a production capacity equal or less than
50 tonnes per day

installations for melting mineral substances including the production of mineral fibres with a melting capacity equal or less than 20 tonnes per day

installations with a production capacity of more than
50 tonnes per day

installations for melting mineral substances including the production of mineral fibres with a melting capacity exceeding 20 tonnes per day

i.    Processing plants for smelting or alloying of non-ferrous metals, including recovered products

foundry plants with smelting capacity below 4 tonnes per day

foundry plants with a smelting capacity exceeding 4 tonnes per day

j.    Ferrous metal foundries

ferrous metal foundries with production capacity below 4 tonnes per day

ferrous metal foundries with a production capacity exceeding 4 tonnes per day

k.    Scrap metal recovery

metal melting or casting: premises on which metal or scrap metal is melted in furnaces or cast when production capacity is more than 100 tonnes per year

premises on which metal scrap is fragmented or melted, including premises on which lead acid batteries are reprocessed when production capacity is less than 100 tonnes per year

metal melting or casting: premises on which metal or scrap metal is melted in furnaces or cast when production capacity is more than 100 tonnes per year

premises on which metal scrap is fragmented or melted, including premises on which lead acid batteries are reprocessed when production capacity is more than 100 tonnes per year

I.    Establishment of plants for plate and container glass manufacturing and glass fibre

when production for plate and glass containers is more than 200 tonnes/year

glass or glass fibre manufacturing: premises on which glass or glass fibre is manufactured when production capacity is less than 200 tonnes/year

when manufacture of glass including glass fibre with a melting capacity exceeding 20 tonnes per day, or

installations for melting mineral substances including the production of mineral fibres with a melting capacity exceeding 20 tonnes per day

m.    Establishment of large scale brick moulding and ceramic products manufacturing plants; premises on which refractory products, tiles, pipes or pottery are manufactured

when production capacity is more than 1,000 tonnes/year

when production capacity exceeding 75 tonnes per day, and/or with a kiln capacity exceeding 4m3 and with a setting density per kiln exceeding 300 kg/m3

Waste Management

a.    Establishment or expansion of waste management facilities

dump sites

incineration plants, boilers or similar activities processing less than 50 kg/hr

Waste Management Facilities (WMF) for recycling of electronic waste

landfills

incineration plants, boilers or similar activities processing more than 50 kg/hr

recovery (for energy) or recycling plants

b.    Radioactive waste storage and disposal facilities

 

all projects

c.    Sewer networks (excluding individual connections to main sewer lines) and associated manholes, sewage pumps stations

 

all projects

d.    Management of hazardous waste

below 5 tons facilities for storage/pre-treatment/treatment/disposal of hazardous waste such as chemicals, (for example, obsolete pesticides or fertilisers), and asbestos or products containing asbestos, electronic equipment, batteries, fluorescent and energy saving bulbs, clinical wastes and other obsolete equipment containing hazardous waste

New treatment technologies for clinical waste (e.g. converters, auto claves, microwaving etc.)

5 tons or more facilities for storage/pre-treatment/ treatment/disposal of hazardous waste such as chemicals, (for example, obsolete pesticides or fertilisers), and asbestos or products containing asbestos, electronic equipment, batteries, fluorescent and energy saving bulbs, clinical wastes and other obsolete equipment containing hazardous waste

e.    Facilities for the treatment or processing of waste such as used tyres, used oil

 

all projects

f.    Facilities for the treatment or processing waste water or polluted ground water

 

all projects

Energy Industry

a.    Construction of facilities for electricity generation

thermal power stations with electricity generation of output equal to or less than 15 MW

construction of facilities for electricity generation using solar with output of less than 5 MW

expansion/upgrading of facilities for electricity generation

thermal power stations with electricity generation of output more than 15 MW

construction of facilities for electricity generation using solar with output of more than 5 MW

b.    Construction of radioactive energy facilities

 

all projects

c.    Construction of petroleum service stations

commercial petroleum service stations and consumer installations with a total capacity of 92 000 litres or more but less than 200 000 litres

commercial petroleum service stations with capacity of more than 200 000 litres

d.    Bulk storage petroleum installations (including storage installations for biofuels)

 

all projects

e.    Construction of liquid petroleum gas facilities

    (i)    liquid petroleum gas (LPG) marketing or commercial installations for distribution to dealers or retailers with total capacity exceeding
92 000 litres and

 

    (ii)    fixed transport structures including LPG pipelines

f.    Manufacturing or processing plants for the production of energy including coal to liquids, crude oil refining and coal bed methane harvesting

 

all projects

g.    Commercial plants for the manufacture of charcoal and coal briquettes

all projects

 

h.    Construction of all commercial or industrial facilities for the generation, transportation and utilisation of natural gas

 

all projects

i.    Installations for production of biofuels

all commercial facilities with capacity of more than 20 000 litres

 

Infrastructure Developments

a.    Construction of roads (primary, secondary, tertiary and access)

construction of a tarred new road of less than 20 km in length

construction of new gravel road of less than 60 km in length

widening of existing roads by less than 6 meters or the lengthening of an existing road by more than 20 km

construction of a tarred new road of more than 20 km in length

construction of new gravel road of more than 60 km in length

b.    Fencing of roads

fencing of roads of less than 20 km in length not located in wildlife reserves or migration routes

fencing of roads of more than 20 km in length

fencing of roads located in protected areas and in known migration routes for wildlife

c.    Construction of tunnels

construction of tunnels less than 100 m

construction of tunnels longer than 100 m

d.    Construction of bridges over water courses

when length is more than 100 m but less than 1 km

when length is more than 1 km

e.    Infrastructure developments such as aerodromes, air fields, airports, airstrips

airstrips, aerodromes

airports and air fields

f.    Construction of dams, levees, barrages, or weirs affecting the flow of river

levees, barrages, or weirs affecting the flow of river

construction of dams with capacity of more than
50,000 m3 or wall higher than 5 m

g.    Construction of well-fields

construction of well-fields where total abstraction of water will be less than 10,000 m3 per day

construction of well-fields where total abstraction of water will be more than
10,000 m3 per day

h.    Intention recharging of an aquifer with any waste water

 

all projects

i.    Construction of canals, channels, river diversions or water transfer schemes between catchments

construction of canals or channels equal or longer than 250 m and shorter than 1,000 m

construction of canals or channels equal or longer than 1,000 m

j.    Development of flood control schemes

 

all projects

k.    Construction of water pipelines and reticulation networks (excluding individual connections)

water pipelines with length of less than 30 km

water pipelines with length exceeding 30 km

I.    Construction of storm water drainage facilities

 

all projects

m.    Construction of telecommunication cables and networks

local access loops and FTTx within one locality
depth 750-800 mm
width 300-400 mm

Backbone projects which stretches from one locality to another
depth 1200 mm
width 400-450 mm

n.    Installation of power lines

power lines outside built up areas with voltage above 66 KVs or inside urban areas with voltage above 132 KVs

expansion of existing power lines when the expanded voltage will be 132 KVs or more

power lines outside built up areas or industrial complexes with voltage of 132KV or more

o.    Installation of power substations

installation of power substations with voltage less than 66 KVs

installation of power substations with voltage of
66 KVs and above

p.    Land reclamation works

area to be transformed larger than 5 Ha in a built up area or larger than 1 Ha outside a built up area

expansions of land reclamation works when the expansion transforms a total area equal or larger than the thresholds mentioned

area to be transformed larger than 20 Ha in a built up area or larger than 10 Ha outside built up area

q.    Development of industrial estates

area equal or larger than 5 Ha in a serviced area or equal or larger than 10 Ha outside unserviced area

expansions of industrial estates when the expansion transforms a total area equal or larger than the thresholds mentioned

area equal or larger than
20 Ha in a serviced area or equal or larger than 10 Ha unserviced area

r.    Development of residential estates

area equal or larger than 5 Ha in an urban area or equal or larger than 1 Ha outside an urban area

expansions of development of industrial estates when the combination of the expansion phases transforms a total area equal or larger than the thresholds mentioned

area is equal or larger than 20 Ha in an urban area or equal or larger than 10 Ha outside an urban area

expansions of development of industrial estates when the combination of the expansion phases transforms a total area equal or larger than the thresholds mentioned

s.    Development of institutional facilities (such as schools, hospitals, etc.)

when the total area to be transformed is larger than 5 Ha inside a built up area or serviced area or larger than 1 Ha outside a built up or serviced area

when the total area to be transformed is larger than
20 Ha inside a serviced or built up area or larger than
10 Ha outside a built up or serviced area

t.    Development of shopping centres or complexes

when the total area to be transformed is larger than 5 Ha inside a built up area or serviced area or larger than 1 Ha outside a serviced area

when the total area to be transformed is larger than
20 Ha inside a built area or serviced area larger than
10 Ha outside a serviced area

u.    Construction of railway lines

when length is longer than
10 km and less than 50 km

upgrade or expansion of railway line to more than 10 km and less than 50 km

when length is longer than
50 km

upgrade or expansion of railway line to more than
50 km

v.    Plants for the manufacture and assembly of motor vehicles

when the total area to be transformed is larger than 5 Ha inside a built up or serviced area or larger than 1 Ha outside an urban area

when the total area to be transformed is larger than
20 Ha inside a built up or serviced area or larger than 10 Ha outside a built up area or serviced area

w.    Establishment of cemeteries and crematoria

when area is more than 2500 m2

expansion of existing cemeteries by more than 2500 m2

establishment of crematoria

 

x.    Construction of facilities for storage of radioactive materials

 

all projects

y.    Construction of subways

 

all projects

z.    Construction camps and camping facilities

 

all projects

Chemical, Rubber and Plastic Industry

a.    Chemical manufacturing or processing plants

when quantity of processed chemicals is less than 2000 kg/month or when production capacity is less than 50,000 tonnes/year

when quantity of processed chemicals is more than 2000 kg/month or when production capacity is more than 50,000 tonnes/year

b.    Chemical manufacturing: premises (other than pesticide manufacturing) on which chemical products are manufactured by a chemical process

when production capacity is more than 100 tonnes/year

when production capacity is more than 1000 tonnes/year

c.    Oil refining plants

 

all projects

d.    Plants for the manufacturing or processing of plastic and rubber where a chemical reaction is involved

 

all projects

e.    Large scale fertiliser, herbicides and pesticide manufacturing or processing plants

 

all projects

f.    Facilities for the manufacture of pharmaceutical products

 

all projects

g.    Bulk storage facilities for hazardous chemicals that:

    i.    Contain at least one carbon to carbon bond; and/or are toxic, harmful, flammable, supporting combustion, corrosive, irritant, sensitising, carcinogenic, mutagenic, toxic for reproduction or hazardous for the environment

    ii.    are liquid (or solid) at STP (standard temperature and pressure)

when stored quantities more than 10 cubic metres but less than 1000 cubic metres in aggregate

when stored quantities are more than 1000 cubic metres in aggregate

Food Industry

a.    Milk processing

milk processing with a production output of more than 500 000 litres to 1 000 000 litres per month

milk processing with a production output of more than 1 000 000 litres per month

b.    Installations of abattoirs

 

all projects

c.    Fish processing plant

with production capacity of more than 100 tons a year but less than 1000 tons per year

with production capacity of more than 1000 tons a year

Leather and Textile Industry

a.    Premises on which animal skins or hides are dried, cured or stored

production or storage capacity of more than 48,000 skins or 12,000 hides per year

production or storage capacity of more than 480,000 skins or 120,000 hides per year

b.    Tanneries

 

all projects

c.    Textile manufacturing operations where dyes are to be used

all projects

 

Wood and Paper Industry

a.    Pulp and paper mills

all projects

 

b.    Wood processing operations or expansion of existing wood processing operations

all projects

 

Firing Ranges and Explosives

a.    Outdoor firing ranges

when located at less than 2 km from a populated zone

when located at more than
2 km from a populated zone

b.    Installations for manufacture of explosives, arms or ammunition or production of explosive substances

quantity produced or stored is more than 250 kg/day

quantity produced or stored is more than 2500 kg/day

c.    Installations for storage or disposal of explosives and ammunition/substances

quantity produced or stored is greater than 250 kg/day

quantity produced or stored is greater than 2500 kg/day

Tourism Enterprises

a.    Hospitality facilities

200 or more guestrooms in an unserviced land

 

Recreation Related Infrastructure

a.    Sports complexes

when the total area to be transformed is larger than 5 Ha but less than 20 Ha inside a built up area

when the total area to be transformed is larger than 2 Ha but less than 10 Ha outside a serviced area

when the total area to be transformed is larger than
20 Ha inside a built up area

when the total area to be transformed is larger than
10 Ha outside a serviced area

b.    Golf courses

 

all projects

c.    Establishment of routes or tracks for outdoor racing of motor powered vehicles such as motorcars, trucks and motorcycles

 

all projects

d.    Amusement parks

all projects

 

Agricultural Projects

a.    Land developments for rain-fed agriculture

 

land developments for rain-fed agriculture in an area larger than 100 Ha

b.    Land developments for irrigated crop farming

large scale horticulture projects in an area measuring more than 50 and less than 100 hectares

large scale irrigated farming projects in an area measuring more than 100 hectares

c.    Fibre and oil (biofuel) crops

land developments for the purpose of fibre and oil (biofuel) crop production in an area less than 50 Ha

land developments for the purpose of fibre and oil (biofuel) crop production in an area larger than 50 Ha

d.    Large scale horticulture projects

large scale horticulture projects in an area measuring more than 50 and less than 100 hectares

large scale horticulture projects in an area measuring more than 100 hectares

e.    Large scale dairy farms

stock rate of more than 50 cows and less than 100

stock rate of 100 or more cows

f.    Large scale feedlots

with stock rate of more than 250 and less than 500 cows

with stock rate of 500 or more cows

g.    Large scale ostrich farms

stock rate of more than 250 and less than 500 birds

stock rate of 500 or more birds

h.    Large scale pig farms

stock rate of more than 50 sow units but less than 300 sow units

large scale pig farms with stock rate of more than 300 sow units

i.    Large scale pig farms of piglets for weaner scheme

more than 500 and less than 1000 piglets for weaner scheme

more than 1000 piglets for weaner scheme

j.    Large scale crocodile farming production systems

less than 4000 m3 pond capacity where there is direct discharge from the production system to the environment;

or

farms with a capacity for more than 200 and less than 1200 crocodiles

more than 4000 m3 pond capacity where there is direct discharge from the production system to the environment;

or

farms with a capacity for more than 1200 crocodiles

k.    Establishment game or livestock farm or ranch

in an area measuring more than 100 hectares and less than
5 000 hectares

in an area measuring more than 5 000 hectares

I.    Large scale poultry farms

with stock rate of more than
20 000 birds but less than
40 000 birds

with stock rate of more than 40 000 birds

m.    Irrigation of any land with waste water generated through industrial activity or by any water works

 

all projects

n.    Introduction of new crops, plants and animals, including Genetically Modified Organisms and Living Modified Organisms

 

all projects

o.    Establishment of fences which are designed to control wildlife and livestock diseases

When fence is more than 5 km in length but less than 20 km

when fence is more than
20 km in length

p.    Construction of fish farming systems

with pond capacity of less than 4000 m3; where there is any direct discharge from the production system to a receiving water body;

or

commercial fish farming venture with an annual production of more than 20 tonnes but less than 40 tonnes

with pond capacity of more than 4000 m3; where there is any direct discharge from the production system to a receiving water body;

or

commercial fish farming venture with an annual production of more than
40 tonnes

q.    Logging operations

establishments covering area of more than 50 hectares but less than 500 hectares

establishments covering an area of more than
500 hectares

r.    Forest plantations, woodlots and tree nurseries

establishments covering an area of more than 50 hectares but less than 500 hectares

establishments covering an area of more than 500 hectares

s.    Small stock (goats and sheep) farms

farms with stock rate of more than 1000

farms with stock rate of more than 5000

Others

a.    A project likely to affect any area protected by the laws of Botswana or such other regional or international laws or conventions

 

all projects

b.    A project whose implementation will likely cause a public outcry or will result in the displacement of people

 

all projects

c.    A project likely to give rise to particular complex or adverse effects whose management is not well understood

 

all projects

d.    A project whose implementation will result in substantial use of a natural resource in a way that prevents the use or potential use of the resources for any other purpose

 

all projects

e.    any activity aimed at the modification of atmospheric precipitation

 

all projects

 

SCHEDULE 2

 

REPUBLIC OF BOTSWANA

Ministry of Environmental Wildlife and Tourism

Department of Environmental Affairs

Telephone: (267) 3902050
Fax: (267) 3902051/3914687
E-mail: envirobotswana@gov.bw

Private Bag 0068
Gaborone
Botswana

All Correspondence to be addressed to the Director

 

    REF: DEA/BOD/ ………………………… RECEIPT No …………………………… DATE………………….

FORM A

(reg. 4(i))

PROJECT BRIEF

Instructions for completing the project brief:

The project brief is to be completed in full and submitted after payment of the application fee in accordance with section 6(2) of the Environmental Assessment Act. Please note that the proof of payment is required at the time of submission of the application.

Please note that all sections of the form must be completed and additional information about the project should be attached to the form where the space provided is not sufficient (alterations of the form shall not be permitted).

Any person who provides false information in the project brief fraudulently is liable to a penalty under section 12(4) of the Act.

To ensure that the implementation of planned activity is not delayed, the project brief should be submitted at the time when a project concept is being considered or at the prefeasibility stage of the project cycle.

Please note that where it is determined by the competent authority that an environmental assessment study is required, the details and certificate of practice of the practitioners whom the developer intends to deploy, shall be submitted to the competent authority by the developer prior to undertaking the environmental impact assessment in accordance with the Environmental Assessment Regulations.—

SECTION A:

Applicant details

Name of project:

 

Estimated project cost:

 

Project proponent: Contact person:

 

Postal address: Physical address:

 

Telephone no: Fax no: E-mail address:

 

Project location: (Location map should be
attached
)

 

 

SECTION B:

1.    Project details:

    a.    Provide a brief description of the project.

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

    b.    What is the physical scale or the size of the development?

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

    c.    What is the anticipated lifespan of the project within the foreseeable or predicted future?

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

2.    Project processes: (Attach project flow diagram and photos where applicable.)

    a.    What are the materials that the activity shall use, including both construction materials and inputs ?

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

    b.    What are the possible products and by-products including waste generation of the activity?

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

3.    Planning issues:

    a.    Has land been allocated for the proposed project? …………………………………………………….

        (Attach supporting documents where applicable)

    b.    What is the current land use of the area or site for the proposed project?

        ……………………………………………………………………………………………………………………………………….

    c.    Will the proposed development require a change in land use? ………………………………….

        (If yes, attach letter of approval for change of land use)

    d.    Are the following services available in the area where the development is to be located?

        Roads ………………………………………………………………………………………………………………… (specify)

        Water ………………………………………………………………………………………………………………….. (specify)

        Power ………………………………………………………………………………………………………………….. (specify)

        Telecommunications ………………………………………………………………………………………….. (specify)

        Sewerage system ………………………………………………………………………………………………. (specify)

        Waste management system ………………………………………………………………………………. (specify)

        Other ……………………………………………………………………………………………………………………. (specify)

        ……………………………………………………………………………………………………………………………… (specify)

    e.    Will the development result in displacement of people or property?

        ……………………………………………………………………………………………………………………………………….

        If yes, how many people or number of households will be affected?

        ……………………………………………………………………………………………………………………………………….

    f.    What is the (approximate) distance of the proposed site from the following land uses

        i.    residential …………………………………………………………………………………………………………….

        ii.    industrial ………………………………………………………………………………………………………………

        iii.    commercial ………………………………………………………………………………………………………….

        iv.    agricultural (arable/pastoral) ………………………………………………………………………………..

        v.    civic & community (e.g church, school, park, etc)

    g.    Is the project located within or near any of the following areas? Specify the distance.

Area

Yes

No

Approximate distance

National park/game reserve

 

 

 

Wildlife management area

 

 

 

Wetland (river, stream, dam, pans or any other areas with open surface water (whether seasonal or perennial)

 

 

 

Flood plains

 

 

 

Important breeding areas for fauna

 

 

 

Areas containing rare or endangered flora and fauna

 

 

 

Important archaeological, historical, religious or cultural sites

 

 

 

Areas protected under legislation

 

 

 

Hilly areas

 

 

 

 

SECTION C:

1.    Outline the possible impacts of the project on the environment (biophysical and socio-economic) in terms of:

    a.    Negative impacts

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

    b.    Positive impacts

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

    c.    What measures will be undertaken to address the negative impacts?

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

    d.    Provide any additional information that may assist in the evaluation of the application.

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

        ……………………………………………………………………………………………………………………………………….

SECTION D:

I …………………………………………………………………………… certify that the information provided is

to the best of my knowledge true and correct.

Signed: ……………………………………………………………..

Date: ………………………………………………………………..

FORM B

(reg. 5)

 

REPUBLIC OF BOTSWANA

Ministry of Environmental Wildlife and Tourism

Department of Environmental Affairs

Telephone: (267) 3902050
Fax: (267) 3902051/3914687
E-mail: envirobotswana@gov.bw

Private Bag 0068
Gaborone
Botswana

All Correspondence to be addressed to the Director

 

CONTENT OF THE ENVIRONMENTAL MANAGEMENT PLAN

This guideline facilitates the standardisation of the Environmental Management Plan (EMP). An EMP will usually be necessary where the proposed project does not qualify for the undertaking of a detailed environmental impact assessment study, but by virtue of the associated impacts would require the development of an environmental management programme to manage the implementation of the project. The EMP may also be required for projects which were implemented prior to the enactment of the EIA legislation but would have otherwise required a detailed assessment prior to their implementation.

The EMP should contain information required by this guideline in accordance with the requirements of the Act. However, the contents should not be taken as static. They are allowed to vary with proposed management actions, complexity and likely impacts which come with different projects in different sectors. In this regard the content of the EMP would be allowed to vary only as one sector varies from the other in terms of complexity of the sector or the nature of its impacts on the environment. The structure and content of the EMP prescribed here should therefore at the minimum contain the following:

a.    The name of applicant and consulting team:

    The name of the applicant as well as the consulting company (or team of companies), should be clearly written on the cover page of the report. This information including postal addresses, telephone number(s), telefax, email as well as the practitioners registration number should be clearly indicated on the first page of the report.

b.    Executive summary (also referred to as a non-technical summary):

    The executive summary should be a concise summary of the report, briefly describing the project, location, the proponent and the organisation undertaking the environmental assessment. Furthermore, the methodology used during the study, expected impacts, management measures as well as recommendations and conclusions should be highlighted.

c.    Introduction:

    The introduction should provide a discussion of the nature of the project proposed, its location, and if the project is part of a larger proposal. The project developer must be clearly identified, as must be the consulting team who carried out the assessment. It should outline the background to the project and the reasons or necessity of it.

d.    Policy, legal and administrative framework:

    This section should identify and discuss in detail the relevance of the policies, legislation, regulations, plans, guidelines as well as planning and implementation approvals which have a bearing on the proposed project. This includes national laws and regulations on EIA, environmental guidelines if they exist, regional, relevant international conventions, and local regulations, environmental assessment regulations of any financing organisations and relevant corporate environmental policies.

e.    Description of the project:

    Information on the description of the project should include but not be limited to the following—

    •     purpose of project;

    •     status of the project in the project cycle: pre-feasibility, feasibility, detailed engineering and design, implementation (construction), operational, decommissioning;

    •     location of proposed project on a map;

    •     preliminary design (if available), infrastructural requirements and size of the development;

    •     anticipated duration of construction (where applicable), operation, close down;

    •     transport and access arrangements;

    •     overall operation of processes involved;

    •     type and quantity of resources used; and

    •     estimated type, quantity, composition, strength of residues or emissions; and processes for the containment, treatment and disposal of wastes.

f.    Description of baseline environment:

    The EMP document should provide an appraisal of dimensions of the study area and descriptions of relevant physical, biological and socio-economic conditions as this is important for future monitoring and auditing. Current and proposed developments in the area should also be taken into account. An evaluation of the local, district, and national development plans is especially important in this regard together with latest information from the Central Statistics Office.

g.    Stakeholder consultation:

    This section should discuss the objectives, methods and results of consultations under-taken with the Interested and Affected Parties (IAPs) as well as the relevant institutional stakeholders. A record of all stakeholders consulted as well as the minutes of the consultation meeting(s) should be annexed to the report. It should be noted that it is not mandatory for the developer to publicise the activity in the mass media as per section 7(2)(a) of the Act nor will the developer be obliged to prepare and submit the scoping report and terms of reference for developing the EMP. However where it is deemed necessary, the competent authority may at its discretion, require for such.

h.    Identification and assessment of environmental impacts:

    This section forms the basis for any mitigation or enhancement action. Impact identification refers to the listing or qualitative and quantitative description of potential impacts that will result from the implementation of a project. This should include a description of the impacts for all the project phases that is, pre-construction, construction, operational and decommissioning phase. The causes for such impacts should also be identified. The description often captures the characteristics of the impacts which include—

    •     Positive and negative: Negative impacts harm, degrade or impair the ecosystem health and the health and quality of life of people who live and work in the affected ecosystems. Some impacts can be perceived to be neutral, whilst others are positive;

    •     Direct and indirect: Direct impacts are created directly by a project action (for example, displacement of people caused by the construction of a dam). Indirect impacts result from subsequent impacts caused by the direct impacts (reduction in living standards for the displaced people). Direct impacts are more easily identifiable and quantifiable than indirect impacts;

    •     Long term and short term: Some impacts occur only during the construction phase of the project (short term), others persist to the operational phase (medium term) and others linger on long after the project has been decommissioned (long term);

    •     Recurring and non-recurring: Some impacts occur repeatedly in space and time, while others occur only once;

    •     Regional and local: Some impacts cover large areas whilst others are restricted to a small area;

    •     Cumulative and non-cumulative: Cumulative impacts result when impacts from one activity combine with those from another activity to produce a greater impact or a different impact. Non-cumulative impacts do not accumulate in space and in time; and

    •     Reversible and irreversible: This refers to the permanence of an impact. Impacts maybe reversible by natural means at natural rates (for example, sand deposition) or through human intervention (for example, reforestation). However, some impacts are irreversible such as the elimination of particular wildlife habitats through urban development.

    Some common methods used to identify impacts include: checklists, matrices and impact networks. Impact assessment deals with the evaluation of the impacts. Having established the range of impacts associated with a development project, it is necessary to predict their magnitude and significance. In general terms, this relies upon baseline studies to establish environmental conditions prior to the project, forecasting methods to predict future conditions, with and without the project, and comparison with environmental standards, and guidelines where appropriate. Evaluation also captures the time period for which impacts are predicted (when they are going to occur and whether short term or long term) and the distribution of the impact (in time and space). Thus after evaluation, the change brought about by an impact can be said to be slight, moderate or substantial, or better still, quantified (for instance the opening up a diamond mine can result in employment levels going up by 60% in an area). Impacts can also be determined to be significant or insignificant after the evaluation. Methods used in the prediction and evaluations of impacts such as those listed below should be discussed before the identification and evaluation of impacts:

    •     Interaction matrices;

    •     Geographic information systems;

    •     Ranking and weighting; and

    •     Mathematical models.

i.    Analysis of alternatives:

    Proposed investment design, site, technology and operational alternatives should be compared systematically in terms of their potential impacts, capital and recurrent costs, suitability under local conditions and institutional, training and monitoring requirements. To the extent possible, for each of the alternatives (including the “no action alternative”), the environmental costs and benefits should be quantified and economic values attached where feasible. Alternatives can be grouped under the following headings and will be relevant at the different stages in the project cycle—

    •     Demand alternatives (for example, using energy more efficiently rather than building more generating plants);

    •     Activity alternatives (for example, providing public transport rather than increasing road capacity);

    •     Location alternatives (either for the entire proposal or for the component (for example, the location of the processing plant for a mine);

    •     Process alternatives (for example, reuse of “waste products” in production, reuse of water, process-optimising and waste reduction, use of more energy or resource efficient processes); and

    •     Input alternatives (for example, raw material, energy sources).

j.    Mitigation Measures:

    Mitigation is the development of practical measures to reduce adverse impacts on the environment, or to enhance the beneficial aspects of an action. Thus mitigation seeks to:

    •     Find ways of implementing projects with minimum environmental costs;

    •     Minimise or eliminate negative impacts;

    •     Ensure the health and safety of workers or employees;

    •     Enhance the benefits of a proposal; and

    •     Protect the public and individual rights to compensation.

    Feasible and cost-effective measures which will reduce potential environmentally significant impacts to acceptable levels should be proposed including capital and recurrent costs, and institutional and training requirements of those measures estimated. There should be clear responsibility for the proposed actions stated, timelines given for implementing the measures and an estimated cost provided. Mitigation is an encompassing term to denote actions that serve to avoid, reduce or compensate for adverse impacts and promote or increase the beneficial impacts of a project. Elements of mitigation thus include—

    •     Avoidance-this implies avoiding projects or activities that could result in adverse impacts;

    •     Minimisation-this refers to minimising the degree, extent, magnitude or duration of adverse impacts. Minimising project impacts can be achieved through

        •     project design modification;

        •     use of alternative site (location);

        •     use of alternative raw materials;

        •     change of production systems; and

        •     use of cleaner production technologies.

    •     Rehabilitation-this refers to rectifying adverse impacts by repairing or enhancing the affected resources;

    •     Restoration-this is an extreme form of rehabilitation and typically requires an extensive engineering of a selected resource to achieve what might be considered original state. It should be borne in mind that once a habitat is destroyed it is extremely difficult to recreate it to the original state;

    •     Replacement-this is compensation for the loss of a natural resource at a location with the creation or protection of the same natural resource (or one similar in nature), at another location; and

    •     Compensation-this refers to the awarding of financial or material benefits to people affected by the project (especially those who have lost their homes and livelihoods).

k.    Archaeological Impact Assessment:

    A summary of the findings and recommendations of the Archaeological Impact Assessment should be discussed. Reference should be made to the detailed findings and recommendations which should form part of the appendices.

l.    Impact mitigation and monitoring plan:

    This section represents the actualisation and the administration of the implementation of mitigation measures, including monitoring, in all the project phases. The EMP document should present, in a tabular format (landscape orientation), the plans for the mitigation and monitoring of identified impacts. It is also necessary to have a decommissioning (remediation and rehabilitation) programme for projects. No matter how long the project lifespan, decommissioning must be considered at the time of project planning. Therefore impacts related to the decommissioning phase and a plan for addressing such impacts should also be provided.

    Mitigation Plan:

    The impact mitigation plan should be presented in a manner in which impacts will be managed and for clarity of presentation this should be tabulated. This should, at the minimum contain—

    •     the phase of the development;

    •     the activities or processes where impact is likely to emanate;

    •     the impacts that need to be mitigated;

    •     the mitigation objectives for each impact;

    •     the mitigation measures or specific actions required to achieve the mitigation objectives;

    •     resources required for mitigation;

    •     estimated costs for mitigation measures; and

    •     responsibility for implementing mitigation measures.

    Monitoring Plan:

    The consulting team will, on the developer’s behalf, design a monitoring plan that is workable. A monitoring scheme for any project is designed to, among other things, check the compliance of the activities of the project against set standards and regulations. Monitoring is also important for checking the performance of the project against set targets. The monitoring plan will enable the project to comply with regulatory requirements as well as help to verify the accuracy of impact prediction. The responsibility of government agencies and developer in implementing the monitoring plan should be outlined. Monitoring should cover both the short term and long term. It is important to point out that the responsibilities of monitoring in the EA Act are assigned to the relevant technical department or local authority. The developer is required by the EA Act to submit an evaluation report on monitoring to the relevant technical department or local authority. The monitoring data will function as an “early-warning system” indicating if an impact is occurring and allowing action to be taken to remedy the situation if data show existence of a trend likely to result in an unacceptable impact in the near future.

    The monitoring plan should be presented in a manner in which impacts will be monitored and should at the minimum contain—

    •     phase of the development;

    •     impact;

    •     parameter to be monitored;

    •     source or location of monitoring;

    •     method of indicating that the mitigation measures have been successful (key performance indicator);

    •     methods of monitoring;

    •     responsible agent for monitoring;

    •     frequency of monitoring;

    •     reporting mechanism;

    •     thresholds or existing standards; and

    •     recommended action if threshold is exceeded.

    Decommissioning Programme:

    Different projects have different life spans, some long and some short. Similarly, some projects gradually decommission at the end of their lifespan, but for some decommissioning is sudden and the effects are tremendous. It is essential therefore to incorporate decommissioning in the overall planning process. A decommissioning plan or programme should contain the following as a minimum—

    •     a projected estimate of the life span of the project;

    •     briefly identify impacts that would result from the decommissioning process and how these would be managed; and

    •     provide a rehabilitation or restoration plan.

m.    Conclusions and Recommendations:

    Appropriate conclusions should be drawn from the report. It is important to have these conclusions summarised in a series of brief statements referring to relevant sections of the EMP document. This conclusion should focus on the methodology, significant impacts, the measures proposed to avoid or mitigate them and the impact management proposals for project implementation. This section should also contain recommendations to the project. Each recommendation should be presented separately and numbered, and should be concise and very clear.

n.    References:

    The report should have a list of references used in the study. The references should be presented in alphabetical order.

o.    Appendices:

    Appendices contain information not directly useful in the text of a report but needed for reference or detailed review by technical expects. The list of appendices should include—

    •     sources of data and information;

    •     all individuals and agencies consulted for specialist information or knowledge used in the report referred to in the text;

    •     written opinions received from outside specialists;

    •     Field data collection programmes completed during the study;

    •     findings of the Archeological Impact Assessment;

    •     detailed data reduced for use in the main body of the report;

    •     detailed technical analysis of particular impacts (for example, pollution dispersal, soil erosion, demands for social services);

    •     detailed location plan and technical maps, designs, drawings, photographs, flow diagrams, etc;

    •     summary of the programme for consulting the public in project planning and assessment, plus a complete record of all parties (stakeholders) consulted and minutes of the meetings;

    •     names, curriculum vitae and roles of the team members who carried out the study; and any other relevant information.

FORM C

(reg. 6)

 

REPUBLIC OF BOTSWANA

Ministry of Environmental Wildlife and Tourism

Department of Environmental Affairs

Telephone: (267) 3902050
Fax: (267) 3902051/3914687
E-mail: envirobotswana@gov.bw

Private Bag 0068
Gaborone
Botswana

All Correspondence to be addressed to the Director

 

SCOPING EXERCISE AND REPORT

A.    Scoping Exercise

1.    Scoping is a process of interaction between interested and affected parties (IAPs), government agencies and proponents. In undertaking scoping applicants (proponents or project developers should be aware of the role played by scoping in the Environmental Impact Assessment (EIA) process.

2.    The objectives of scoping in the EIA process—

    The objectives of scoping in the EIA process include

    •     focusing the EIA study so that only relevant and important issues are addressed by the EIA;

    •     refining time or space boundaries for the EIA;

    •     to facilitate an efficient assessment process that saves time and resources and reduces costly delays;

    •     identifying the possible effects of the proposal;

    •     considering reasonable and practical alternatives;

    •     to allow a prioritisation of the issues to be addressed;

    •     to organise, focus and communicate the potential impacts and concerns, to assist further analysis and decision making; and

    •     most importantly, establishing the terms of reference (ToRs) to be used as the basis of the ongoing assessment.

3.    Identifying interested and affected parties (IAPs)

    An important aspect of the scoping exercise is the identification of interested and affected parties (stakeholders) to be involved in the scoping exercise. These will differ from project to project. The following are some of the IAPs that should be involved in the scoping exercise. Their different roles are also summarised:

    •     The project developer (if the applicant has hired a practitioner to lead the scoping exercise): usually knows most about the proposal and will know most about the factors that influence site location. The scoping exercise will allow the project developer to recognise the perspective of others, to consider alternatives and issues of concern raised by those affected, and to make changes to the proposal which will both address the concerns raised and improve the proposal;

    •     The competent authority will have the procedural requirements for the scoping and may issue directives on the scope of the EIA;

    •     Other government agencies: will contribute detailed knowledge about specific issues under their jurisdiction;

    •     Environmental practitioners and experts;

    •     Licensing or permitting authorities such as local Land Boards, Department of Mines, Town and Country Planning Board, National Industrial Licensing Authority, Local Authorities, etc.;

    •     Those Affected: have a major role in identifying issues and ensuring that local knowledge and values are understood. The views of those affected should be taken into account in choosing between alternatives, in deciding on the importance of issues, and in framing mitigation measures, compensation provisions and management plans;

        •     Local authorities including local government, tribal leadership (Dikgosi); and

        •     The wider community including local, national and sometimes international NGOs.

    Designing the public participation or consultation plan

    The Consultation plan will indicate the IAPS to be consulted; the method that would be used for consultation and the venues and times of consultation. In designing the consultation plan, the applicant should consider relevant methods for consulting different stakeholders including the following:

    •     Questionnaire, polls and surveys: to determine public attitudes and perceptions on various issues;

    •     Advertisement: public notices describing the details of the project and issues involved placed at accessible locations;

    •     Mass media: use of newspapers, TV and radio coverage to reach a large proportion of the community;

    •     Leafleting: brochures, leaflets and information sheets distributed to the public as a quick and easy method of providing general information;

    •     Personal contact: direct discussions between project staff and individuals interested in the effects of the project;

    •     Community presentations: presentations given by the developers specific community groups;

    •     Workshops: Generally most effective for discussing and identifying solutions to problems, scoping of potential impacts and creating other plans of action;

    •     Public meetings: meetings by the developer to make a presentation describing the project and the relevant issues, which is then followed by a question and answer session; and

    •     Public hearings and inquiries: more formal than public meetings.

4.    Undertaking the Scoping Exercise

    Once the public consultation plan has been finalised, the applicant should proceed with the scoping exercise as set out in the plan taking note of the provisions of the Act, section 7(2) which states that in seeking the views of the people or communities, the applicant shall—

    •     Publicise the intended activity, its effects and benefits in the mass media using the official languages for a period not less than 21 days, and

    •     After the expiry of the period of 21 days, hold meetings with the affected people or communities to explain the activity and its effect.

B.    Scoping report

    After completing the scoping exercise, the applicant should produce a scoping report to be submitted to DEA. The content of the report should at the minimum, include the following—

    •     Introduction and background information

    This section should include:

    –    A brief description of the major components of the proposed project including location (provide maps where possible), general layout; size, capacity; preconstruction activities, construction activities; schedule, staffing and support; facilities and services, operation and maintenance activities; required off-site investments; and life span, justification for the project and the objectives it is intended to meet, its current status and timetable and the identities of any associated projects.

    –    Details of the proponent and the consulting team undertaking the environmental assessment study;

    –    The project location with a brief description of the baseline environment (biophysical and socio-economic);

    –    The purpose and objectives of the scoping exercise;

    –    The boundaries where the scoping exercise focused;

    –    The methodology being used for the scoping exercise and the description of the public participation process in terms of identification of IAP’s; establishment and record of procedure by which the identified and non-identified IAPs were afforded the opportunity to participate; provision for IAP’s to express their views about the scope of the EIA, including alternatives that were investigated; list of issues identified as being of concern to IAPs; and notification criteria (reason for participation, where, when and to whom comments can be sent).

    •     Outcomes of the scoping exercise

    This section should:

    –    Identify and briefly discuss any policies, legislation, regulations, plans, guidelines, etc. which impact on the proposed planning, development and operation of the proposed project;

    –    Describe the environmental issues identified including the definable impacts and their causes; and

    –    Summarise the views of stakeholders (including local communities) who were consulted. (Note that the list of interested and affected parties consulted, minutes of the consultation meetings and advert for the public meetings should be annexed to the scoping report).

FORM C1

(reg. 5A)

Contents of the Rehabilitation Plan

    i.    Rehabilitation Plan

    Rehabilitation Plan means an outline of measures for the treatment or management of disturbed land, air or water for the purpose of establishing a safe and a stable environment. Information on the description of the project should include but not limited to the following—

    •     purpose of project;

    •     location of proposed project on a map;

    •     area to be rehabilitated;

    •     anticipated duration of the project;

    •     transport and access arrangements;

    •     overall processes involved in the rehabilitation;

    •     type and quantity of resources needed for rehabilitation; and

    •     expected outcome of the rehabilitation process.

    ii.    Contents of the Waste Management Plan

    Waste Management Plan means an outline of waste stream and treatment options comprising of the collection, temporary storage and safe disposal of the waste streams associated with an activity and includes provisions for the recovery, re-use and recycling of waste.

Information on the description of the project should include but not limited to the following—

    •     purpose of project;

    •     location of the proposed project on a map;

    •     preliminary design (if available), infrastructural requirements and the size of the development;

    •     transport and access arrangements; and

    •     overall operation of processes involved.

The Waste Management Plan should be presented in a manner in which impact will be managed. This should at the minimum contain—

    •     process flow diagram;

    •     type(s) of waste;

    •     estimated quantities;

    •     anticipated types of residues or emissions;

    •     containment measures on site;

    •     methods for treatment; and

    •     disposal methods.

FORM D

(reg. 7)

 

REPUBLIC OF BOTSWANA

Ministry of Environmental Wildlife and Tourism

Department of Environmental Affairs

Telephone: (267) 3902050
Fax: (267) 3902051/3914687
E-mail: envirobotswana@gov.bw

Private Bag 0068
Gaborone
Botswana

All Correspondence to be addressed to the Director

 

TERMS OF REFERENCE

Terms of Reference

The Terms of Reference (ToR) define all issues or the scope of work on which the EIA study will focus. The information provided below should only be used as a guide since projects, their status in the project cycle, and proponent needs vary widely and, thus, ToR contents cannot be standardised.

Nonetheless, the report should have an introduction which should state the purpose and objectives of the ToRs and identify the development project to be assessed. It should also summarise the general scope of the environmental assessment and discuss its timing in relation to the processes of project preparation, design and implementation. The boundaries for the study area for the assessment should also be specified.

    A description of all the tasks to be performed in the EIA study should be provided and should, at a minimum, include:

    •     Policy and regulatory framework:

        The ToRs should outline any policies, legislation, regulations, plans, guidelines as well as planning and implementation approvals which impact on the proposed project, the relevance of which should be discussed in detail during the EIA phase.

    •     Description of the environment:

        The baseline data on the relevant environmental characteristics of the study area to be discussed in the EIA should be highlighted. The discussion in the EIA should present and evaluate the baseline environmental aspects of the study area and highlight any anticipated changes before the project commences. The description of the environmental baseline should include:

        •     Physical environment:

        •     Biological environment:

        •     Socio-cultural environment (both present and projected where appropriate)

    •     Public consultation:

        The ToRs should require that a consultation programme be clearly presented in the EIA report (that is, objectives of scoping exercise, methods used for consultations and outcomes of the consultations). Any further consultations to be undertaken with the IAPs during the EIA study should be indicated in the ToRs.

    •     Analysis of alternatives to the proposed project:

        Describe alternatives that would be examined in the course of developing the proposed project and identify other alternatives which would meet the same objectives.

    •     Prediction and assessment of the potential impacts for the proposed project:

        This is the major activity of the EIA process. There are a wide range of tools available to the EIA practitioner for predicting the impacts of a proposed activity. This section should include an outline of the environmental impacts to be assessed as well as the methods and criteria to be used to judge impact severity and significance (that is, the methodology and criteria used for impact identification, impact analysis and impact assessment such as check lists; matrices; overlays; impact networks; simulation models; ranking and weighting; surveys; public consultations; analysis of the severity of impacts; and appraisal of how significant these impacts are likely to be).

    •     Presentation of mitigation measures:

        The need for the EIA to address measures for avoiding, mitigating and managing impacts should be clearly stated. The ToRs should indicate that the consulting team will recommend feasible and cost-effective measures to prevent or reduce significant negative impacts to acceptable levels and enhance positive impacts.

    •     Development of an environmental management plan:

        While the project is in operation within the environment, it is necessary to have an EMP in place that will determine how the impacts of the project are handled. The ToRs should indicate the structure to be used for the EMP, which should normally incorporate any necessary monitoring and the identification of institutions responsible for implementing the monitoring program. The EMP should also contain a plan for decommissioning of the project.

    •     Archeological Impact Assessment (AIA):

        The EIA and AIA should be carried out concurrently. The applicant shall check with the Department of National Museum and Monuments to comply with the Monuments and Relics Act (Cap. 59:03). The applicant should indicate in the terms of reference whether an AIA will be carried and the level to which it will be carried out.

    •     Report:

        The environmental assessment report should be concise and limited to significant environmental issues. This section should describe the structure that will be used for the report.

FORM E

(reg. 8)

 

REPUBLIC OF BOTSWANA

Ministry of Environmental Wildlife and Tourism

Department of Environmental Affairs

Telephone: (267) 3902050
Fax: (267) 3902051/3914687
E-mail: envirobotswana@gov.bw

Private Bag 0068
Gaborone
Botswana

All Correspondence to be addressed to the Director

 

CONTENT OF THE ENVIRONMENTAL IMPACT STATEMENT

This guideline facilitates the standardisation of the Environmental Impact Statements (EIS). An EIS should contain information required by the Act. However, the contents should not be taken as static. They are allowed to vary with proposed management actions, complexity and likely impacts which come with different projects in different sectors. In this regard the content of the EIS would be allowed to vary only as one sector varies from the other in terms of complexity of the sector or the nature of its impacts on the environment. The structure and content of the EIS prescribed here should therefore at the minimum contain the following—

a.    The name of applicant and consulting team:

    The name of the applicant as well as the consulting company (or team of companies), should be clearly written on the cover page of the report. This information including postal addresses, telephone number(s), telefax, email as well as the practitioners registration number should be clearly indicated on the first page of the report.

b.    Executive summary (also referred to as a non-technical summary):

    The executive summary should be a concise summary of the report, briefly describing the project, location, the proponent and the organisation undertaking the environmental assessment. Furthermore, the methodology used during the study, expected impacts, management measures as well as recommendations and conclusions should be highlighted.

c.    Introduction:

    The introduction should provide a discussion of the nature of the project proposed, its location, and if the project is part of a larger proposal. The project developer must be clearly identified, as must be the consulting team who carried out the assessment. It should outline the background to the project and the reasons or necessity of it.

d.    Policy, legal and administrative framework:

    This section should identify and discuss in detail the relevance of the policies, legislation, regulations, plans, guidelines as well as planning and implementation approvals which have a bearing on the proposed project. These include national laws and regulations on EIA, environmental guidelines if they exist, regional, relevant international conventions, and local regulations, environmental assessment regulations of any financing organisations and relevant corporate environmental policies.

e.    Description of the project:

    Information on the description of the project should include but not be limited to the following—

    •     Purpose of project;

    •     The status of the project in the project cycle: pre-feasibility, feasibility, detailed engineering and design, implementation (construction), operational, decommissioning;

    •     Location of proposed project on a map;

    •     Preliminary design (if available), infrastructural requirements and size of the development;

    •     Anticipated duration of construction, operation, close down;

    •     Proposed transport and access arrangements;

    •     Overall operation of processes involved;

    •     Type and quantity of resources used; and

    •     Estimated type, quantity, composition, strength of residues or emissions; and processes for the containment, treatment and disposal of wastes.

f.    Description of baseline environment:

    The EIS should provide an appraisal of dimensions of the study area and descriptions of relevant physical, biological and socio-economic conditions as this is important for future monitoring and auditing. Current and proposed developments in the area should also be taken into account. An evaluation of the local, district, and national development plans is especially important in this regard together with latest information from the Central Statistical Office.

g.    Public consultation:

    This section should discuss the objectives, methods and results of public consultations undertaken during the scoping exercise. Where applicable, the methodology utilised for further consultation of IAPs during the EIA, and outcomes of the consultations should also be discussed. A record of all stakeholders consulted as well as the minutes of the consultation meeting(s) should be annexed to the report.

h.    Identification and assessment of environmental impacts:

    This is a crucial part of the EIA process and forms the basis for any mitigation or enhancement action. Impact identification refers to the listing or qualitative and quantitative description of potential impacts that will result from the implementation of a project. This should include a description of the impacts for all the project phases that is, pre-construction, construction, operational and decommissioning phases. The causes for such impacts should also be identified. The description often captures the characteristics of the impacts which include:

    •     Positive and negative: Negative impacts harm, degrade or impair the ecosystem health and the health and quality of life of people who live and work in the affected ecosystems. Some impacts can be perceived to be neutral, whilst others are positive;

    •     Direct and indirect: Direct impacts are created directly by a project action (for example, displacement of people caused by the construction of a dam). Indirect impacts result from subsequent impacts caused by the direct impacts (reduction in living standards for the displaced people). Direct impacts are more easily identifiable and quantifiable than indirect impacts;

    •     Long term and short term: Some impacts occur only during the construction phase of the project (short term), others persist to the operational phase (medium term) and others linger on long after the project has been decommissioned (long term);

    •     Recurring and non-recurring: some impacts occur repeatedly in space and time, while others occur only once;

    •     Regional and local: Some impacts cover large areas whilst others are restricted to a small area;

    •     Cumulative and non-cumulative: Cumulative impacts result when impacts from one activity combine with those from another activity to produce a greater impact or a different impact. Non-cumulative impacts do not accumulate in space and in time; and

    •     Reversible and irreversible: This refers to the permanence of an impact.

        Impacts maybe reversible by natural means at natural rates (e.g. sand deposition) or through human intervention (for example, (reforestation). However, some impacts are irreversible such as the elimination of particular wildlife habitats through urban development.

Some common methods used to identify impacts include: checklists; matrices; and impact networks. Impact assessment deals with the evaluation of the impacts. Having established the range of impacts associated with a development project, it is necessary to predict their magnitude and significance. In general terms, this relies upon baseline studies to establish environmental conditions prior to the project, forecasting methods to predict future conditions, with and without the project, and comparison with environmental standards, and guidelines where appropriate. Evaluation also captures the time period for which impacts are predicted (when they are going to occur and whether short term or long term) and the distribution of the impact (in time and space). Thus after evaluation, the change brought about by an impact can be said to be slight, moderate or substantial, or better still, quantified (for instance the opening up of a diamond mine can result in employment levels going up by 60% in an area). Impacts can also be determined to be significant or insignificant after the evaluation. Methods used in the prediction and evaluations of impacts such as those listed below should be discussed before the identification and evaluation of impacts:

    •     Interaction matrices;

    •     Geographic information systems;

    •     Ranking and weighting; and

    •     Mathematical models.

    i. Considerations for transboundary impacts:

    At times, the environmental impact of a project may be realised across international boundaries. Such an impact is described as “transboundary”. “Transboundary impact” may be defined as any impact, not exclusively of a global nature, within an area under the jurisdiction of a country caused by a proposed activity the physical origin of which is situated wholly or in part within the area under the jurisdiction of another country. There are two distinct scenarios involved in the assessment of such impacts, viz:

    •     The activity is recognised as national and the neighbouring countries do not wish to take part directly in the EIA process, even though its impact extends beyond the national border to their territories, preferring to exercise their right as interested and affected parties only. Under this scenario, the country of origin will share information on its EIA process in a transparent manner and take the concerns of its neighbours into consideration; and

    •     Neighbouring countries, recognising that the proposed activity’s impact will affect them too, may decide to take part in the EIA process directly with the proponent country. In this case, the EIA will be carried out under negotiated terms based on a common international convention to which all the parties are signatory or the respective national EIA processes. In the SADC Region, there is no protocol dealing directly with the conduct of EIA in a transboundary context, as obtains in other regions for example, the Espoo Convention. However, there are protocols on specific areas of co-operation that have significant provisions for dealing with transboundary impacts, for example, the Revised Protocol on Shared Watercourses. These protocols could form the basis for negotiating procedures to adopt for conducting multilateral EIA.

    •     The requirement of environmental impact assessments in respect of activities that are likely to significantly affect the environment enshrined in the Act, in the case of purely domestic impacts, may be extended to cover impacts arising beyond the borders of Botswana that can be attributed to an activity within Botswana. The basis for such extension can be found in several conventions, treaties or agreements to which Botswana is a signatory. For example:

        •     Principle 17 of the Rio Declaration on Environment and Development; Article 5 of the Legal Principle for Environmental Protection and Sustainable Development, adopted by the Experts Group on Environmental Law of the World Commission on Environment and Development;

        •     The 1987 Goals and Principle of Environmental Impact Assessment developed under the auspices of UNEP by the Working Group of Experts on Environmental Law and which were adopted by the UNEP Governing Council at its 14th session, and commended to States to be considered for use as a basis for preparing appropriate national measures including legislation; and

        •     Article 3(10a) of the Revised SADC Protocol on Shared Watercourses, the so-called “No Harms Rule”; and similar obligations imposed by Article 4 of the same protocol making it mandatory to inform neighbours in the event of an incident that has the potential to cause significant harm in the territory of the neighbour.

    All these impose an obligation which must be reflected in the domestic EIA process in as much as transboundary impacts are concerned.

    Procedure for transboundary impacts:

    The procedure to be adopted cannot be much different from the procedures already described for domiciled impacts. Reference should therefore be made to those guidelines. However, there are some areas that require additional input as described below:

    •     Where an activity is likely to have an impact outside the borders, the scoping should reflect this by identifying and consulting interested and affected parties in the neighbouring countries. The assistance of Department of Environmental Affairs (DEA) may be sought to make contact with counterparts in the neighbouring countries;

    •     While public consultations in the manner prescribed in the EA Act may not be feasible in the affected countries, it may be possible to obtain their input via the counterparts of DEA in those countries. In view of this an open reporting system through the DEA may be helpful;

    •     Ensure that concerns raised by the affected country are adequately addressed in the consequent ToR; and

    •     Seek and obtain all relevant information from the affected countries. The DEA may be helpful in this exercise.

j.    Analysis of alternatives:

    Proposed investment design, site, technology and operational alternatives should be compared systematically in terms of their potential impacts, capital and recurrent costs, suitability under local conditions and institutional, training and monitoring requirements. To the extent possible, for each of the alternatives (including the “no action alternative”), the environmental costs and benefits should be quantified and economic values attached where feasible. Alternatives can be grouped under the following headings and will be relevant at the different stages in the project cycle—

    •     Demand alternatives (for example, using energy more efficiently rather than building more generating plants);

    •     Activity alternatives (for example, providing public transport rather than increasing road capacity);

    •     Location alternatives (either for the entire proposal or for the component (for example, the location of the processing plant for a mine);

    •     Process alternatives (for example, reuse of “waste products” in production, reuse of water, process-optimising and waste reduction, use of more energy or resource efficient processes); and

    •     Input alternatives (for example, raw material, energy sources).

k.    Mitigation measures:

    Mitigation is the development of practical measures to reduce adverse impacts on the environment, or to enhance the beneficial aspects of an action. Thus mitigation seeks to—

    •     find ways of implementing projects with minimum environmental costs;

    •     minimise or eliminate negative impacts;

    •     enhance the benefits of a proposal; and

    •     protect the public and individual rights to compensation.

    Feasible and cost-effective measures which will reduce potential environmentally significant impacts to acceptable levels should be proposed including capital and recurrent costs, and institutional and training requirements of those measures estimated. There should be clear responsibility for the proposed actions stated, timelines given for implementing the measures and an estimated cost provided. Mitigation is an encompassing term to denote actions that serve to avoid, reduce or compensate for adverse impacts and promote or increase the beneficial impacts of a project. Elements of mitigation thus include:

    •     Avoidance-this implies avoiding projects or activities that could result in adverse impacts;

    •     Minimisation-refers to minimising the degree, extent, magnitude or duration of adverse impacts. Minimising project impacts can be achieved through:

        •     project design modification,

        •     use of alternative site (location),

        •     use of alternative raw materials,

    •     change of production systems, and

    •     use of cleaner production technologies.

    •     Rehabilitation-this refers to rectifying adverse impacts by repairing or enhancing the affected resources;

    •     Restoration-this is an extreme form of rehabilitation and typically requires an extensive engineering of a selected resource to achieve what might be considered original state. It should be borne in mind that once a habitat is destroyed it is extremely difficult to recreate it to the original state;

    •     Replacement-this is compensation for the loss of a natural resource at a location with the creation or protection of the same natural resource (or one similar in nature), at another location; and

    •     Compensation-this refers to the awarding of financial or material benefits to people affected by the project (especially those who have lost their homes and livelihoods).

l.    Archeological Impact Assessment:

    A summary of the findings and recommendations of the Archeological Impact Assessment should be discussed. Reference should be made to the detailed findings and recommendations which should form part of the appendices.

m.    Environmental Management Plan (EMP):

    An environmental management plan is a tool (document) that represents the actualisation and the administration of the implementation of mitigation measures in all the project phases. Thus an EMP allocates responsibilities, resources and attaches time frames. An important component of the EMP is the monitoring programme to assess progress in the implementation of mitigation measures and compliance of the project to regulations and standards. It is also necessary to have a decommissioning (Remediation and rehabilitation) programme for projects. No matter how long the project lifespan, decommissioning must be considered at the time of project planning. The applicant should address impacts related to the decommissioning phase and a plan for addressing such impacts should be incorporated into the EMP. Thus the EMP will consist of the following components—

    •     impact mitigation plan;

    •     monitoring programme ;and

    •     decommissioning programme.

    Impact mitigation plan:

    The impact mitigation plan should be presented in a manner in which impacts will be managed and for clarity of presentation this should be tabulated. This should, at the minimum contain:

    •     the phase of the development;

    •     the activities or processes where impact is likely to emanate;

    •     the impacts that need to be mitigated;

    •     the mitigation objectives for each impact;

    •     the mitigation measures or specific actions required to achieve the mitigation objectives;

    •     resources required for mitigation;

    •     estimated costs for mitigation measures; and

    •     responsibility for implementing mitigation measures.

    Monitoring plan:

    The consulting team will, on the developer’s behalf, design a monitoring plan that is workable. A monitoring scheme for any project is designed to, among other things, check the compliance of the activities of the project against set standards and regulations. Monitoring is also important for checking the performance of the project against set targets. The monitoring plan will enable the project to comply with regulatory requirements as well as help to verify the accuracy of impact prediction. The responsibility of government agencies and developers in implementing the monitoring plan should be outlined. Monitoring should cover both the short term and long term. It is important to point out that the responsibilities of monitoring in the EA Act are assigned to the relevant technical department or local authority. The developer is required by the EA Act to submit an evaluation report on monitoring to the relevant technical department or local authority. The monitoring data will function as an “early-warning” system indicating if an impact is occurring and allowing action to be taken to remedy the situation if data shows existence of a trend likely to result in an unacceptable impact in the near future.

    The monitoring plan should be presented in a manner in which impacts will be monitored and for clarity of presentation this should be tabulated. This should, at the minimum contain:

    •     phase of the development;

    •     impact;

    •     parameter to be monitored;

    •     source/location of monitoring;

    •     method of indicating that the mitigation measures have been successful (key performance indicator);

    •     methods of monitoring;

    •     responsible agent for monitoring;

    •     frequency of monitoring;

    •     reporting mechanism;

    •     thresholds or existing standards; and

    •     recommended action if threshold is exceeded

    Decommissioning programme:

    Different projects have different life spans, some long and some short. Similarly, some projects gradually decommission at the end of their lifespan, but for some decommissioning is sudden and the effects are tremendous. It is essential therefore to incorporate decommissioning in the overall EIA planning process. A decommissioning plan or programme should contain the following as a minimum:

    •     provide a projected estimate of the life span of the project;

    •     briefly identify impacts that would result from the decommissioning process and how these would be managed; and

    •     provide a rehabilitation or restoration plan.

    For the purpose of presentation, information on the EMP should be tabulated.

n.    Conclusions and recommendations:

    Appropriate conclusions should be drawn from the report. It is important to have these conclusions summarised in a series of brief statements referring to relevant sections of the EIA Report. This conclusion should focus on the methodology, significant impacts, the measures proposed to avoid or mitigate them and the impact management proposals for project implementation. This section should also contain recommendations to the project. Each recommendation should be presented separately and numbered, and should be concise and very clear.

o.    References:

    The report should have a list of references used in the study. The references should be presented in alphabetical order.

p.    Appendices:

    Appendices contain information not directly useful in the text of a report but needed for reference or detailed review by technical expects. The list of appendices should include—

    •     terms of reference for the study;

    •     sources of data and information;

    •     all individuals and agencies consulted for specialist information or knowledge used in the report referred to in the text;

    •     written opinions received from outside specialists;

    •     field data collection programmes completed during the EIA study;

    •     findings of the Archeological Impact Assessment;

    •     detailed data reduced for use in the main body of the report;

    •     detailed technical analysis of particular impacts (for example, pollution dispersal, soil erosion, demands for social services);

    •     detailed location plan and technical maps, designs, drawings, photographs, flow diagrams, etc;

    •     summary of the programme for consulting the public in project planning and assessment, plus a complete record of all parties (stakeholders) consulted and minutes of the meetings;

    •     names, curriculum vitae and roles of the team members who carried out the study; and

    •     any other relevant information.

SCHEDULE 3

[S.I. 49/2021.]

(reg. 4)

 

REPUBLIC OF BOTSWANA

Ministry of Environment, Natural Resources Conservation and Tourism

Department of Environmental Affairs

Telephone: (267) 3902050
Fax: (267) 3902051/3914687
E-mail: envirobotswana@gov.bw

Private Bag 0068
Gaborone
Botswana

All Correspondence to be addressed to the Director

 

FEES CHARGED FOR THE PROVISION OF SERVICES

 

Service Provided

Fee

1.

Review of project brief

P15

2.

Review of environmental assessment reports will be related to project cost as follows:

 

 

Less than P100 000

P140

 

P 100 000 – P499 999

P355

 

P 500 000 – P 999 999

P710

 

P 1 000 000 – P 9 999 999

P1060

 

P 10 000 000 – P 49 999 999

P1415

 

P 50 000 000 or more

P2125

 

Note:     Fees for Environmental Impact Statement and Strategic Environmental Assessment Report includes review of Scoping Report and Terms of Reference.

SCHEDULE 4

FORM A

(reg. 10(1))

Application for Registration as Environmental Practitioner

APPLICATION FORM FOR MEMBERSHIP AND CERTIFICATION

A. CATEGORY OF APPLICATION

 

 

What are you applying for?

General Membership of the Association

 

Certification as an Environmental Practitioner

 

 

B. ENVIRONMENTAL PRACTITIONER APPLICATION

 

This part should be filled only by applicants for certification. Please read guidance notes on
requirements for certification attached at the back of the application form.

What level of Certification are you currently at?
(There are four levels. EAP stands for Environmental Assessment Practitioner)

None

 

Trainee EAP (No experience)

 

EAP

 

Senior EAP

 

Principal EAP

 

What level of Certification are you applying for?

 

 

Trainee EAP

 

EAP

 

Senior EAP

 

Principal EAP

 

What is the status of your current membership?

New/None

 

Active (in Good Standing)

 

Suspended

 

Facing Disciplinary Action

 

Facing Disciplinary Action

 

 

C. PERSONAL DETAILS

NAMES AND SALUTATION

SURNAME

FIRST NAME

MIDDLE NAME

TITLE(Mr/Mrs/Ms/Dr/Prof)

IDENTITY, NATIONALITY & GENDER

OMANG/PASSPORT NO:

COUNTRY OF
CITIZENSHIP

COUNTRY
OF
RESIDENCE

SEX (Tick)

Male

 

Female

 

ADDRESSES

POSTAL ADDRESS

PHYSICAL ADDRESS
(Home)

PHYSICAL ADDRESS (Work)

TELEPHONE & EMAIL CONTACTS

TELEPHONE
NUMBER

CELL PHONE NUMBER

ALTERNATE CELL
NUMBER

EMAIL ADDRESS(ES)

 

D. TERTIARY EDUCATION AND QUALIFICATIONS

TERTIARY EDUCATION AND QUALIFICATIONS (Minimum of 1 year duration)

College/University Attended

Dates Attend (From
YYYY to YYYY)

Title of Study Programme (Qualification
Received)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SHORT COURSES/TRAINING PROGRAMMES (Less than 1 year duration)

College/University Attended

Dates Attend
(Duration From
YYYY to YYYY)

Title of Course (Award

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

E. EMPLOYMENT RECORD (HISTORY)

Dates

Duration (in
Months)

Type of
Employment

Employing
Organisation
(Name,
Location)

Title of
Position
Held

% of Time on
Position

Start

Finish

Full
Time

Part Time
(Temporary,
Internship
etc)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DECLARATION BY APPLICANT

I     (names of applicant) declare

I ………………………………………………………………………………………………… that the information I have provided above is true and correct. I am aware that any false declaration, if discovered, may result in refusal of my membership of the Association or its cancellation if already approved by the Board. I am also aware that the Board reserves the right to take further legal action against me as deemed necessary on account of a false declaration.

……………………………………………………………………     ……………………………………………………………………….
SIGNATURE OF APPLICANT DATE

FORM B

(reg. 10(2))

QUALIFICATIONS AND CRITERIA FOR CERTIFICATION OF ENVIRONMENTAL ASSESSMENT PRACTITIONERS (EAP):

The criteria to be used to assess applications for registration and certification in all levels includes: qualifications in an environmental discipline; applicants must demonstrate that they have been predominantly involved in relevant Environmental Assessment (EA) work experience; and for higher level categories, applicants must demonstrate core competencies in EA.

Detailed below are the qualifications and criteria for certification by the Botswana Environmental Assessment Practitioners Association (BEAPA) Certification Board.

1.    Education and experience required per category of certification

Proposed Category
of EAP

Tertiary qualification from a
recognised university in an
environmental discipline

Relevant working
experience in EIAs at
required level of competency
(see below)

Trainee EAP

Diploma, or Bachelors Degree, or
Graduate Degree

No experience

EAP

Diploma, or
Bachelor’s Degree or
Masters Degree

3 years
2 years
5 years

Senior EAP

Diploma or
Bachelors Degree or
Masters Degree or
Doctorate Degree

5 years
4 years
3 years
2 years

Principal EAP

Diploma or
Bachelor degree or
Masters Degree or
Doctorate Degree

10 years
10 years
6 years
5 years

 

2.    Core competencies:

    The issues considered to constitute core competencies include: holistic thinking; analytical skills; integration and synthesis of biophysical and socio-economic issues; alternatives analysis; competence in each phase of the EA process; application of the principles of sustainable development; understanding of relevant legal and policy requirements; project management skills; subcontracting and management of specialists; communication skills; and reviewing.

    The methods by which core competencies are assessed by the Certification Board differ with the levels of certification categories and these are outlined below:

    (a)     Trainee EAP

        •     Certificates

        •     CV

        •     Refrees’ reports

    (b)    Environmental Assessment Practitioner (EAP)

    •     Structured Interview

        •     CV

        •     Referees’ reports

        •     Diploma/Bachelors degree/Post-graduate certificates

    (c)    Senior EAP

        •     Structured Interview

        •     EA reports

        •     CV

        •     Referees’ reports

        •     Diploma/ Bachelors degree/Post-graduate certificates

    (d)    Principal EAP

        •     Structured Interview

        •     EA reports

        •     CV

        •     Referees’ reports

        •     Diploma/ Bachelors degree/Post-graduate certificates

        •     Other (research papers or presented papers on EA related issues)

3.    Upgrade of Categories:

    Registrants may wish to upgrade to a higher level once they have attained the necessary experience and personal attributes and skills. To do this the applicant will be required to submit:

    (a)    a covering letter stating their intention to upgrade and to which level;

    (b)    log-sheets detailing any EA work they have completed since they first applied to the scheme;

    (c)    a revised personal statement; and

    (d)    portfolios of work and/or a briefing summary depending on level being applied for.

    The upgrade will be considered as a new application and will be charged accordingly.

4.    Certification Process:

    The certification process will be as outlined below:

    •     Applicants must apply for certification using the appropriate application form, depending on the category being applied for;

    •     Forms will be available on a website, or may be requested in writing or by phone or fax from the Secretary of the Board;

    •     The forms must be accompanied by a comprehensive CV, referees’ reports and other documentation as required for the category being applied for;

    •     The confidential reports from three referees: one academic, one professional EAP and one client must be submitted independently;

    •     The application must be accompanied by a fee, which will be non-refundable in the event that the application fails. The application fee will also include the first year’s registration fee if the application is successful;

    •     Applications must be submitted at least two weeks before the monthly/quarterly/ bi-annual Board review meeting to the Secretary by email, fax, post, courier or personal delivery;

    •     The Board will review applications strictly in the order received;

    •     The applicants will receive a response no more than two weeks after the Board review meeting;

    •     Successful applicants will be issued with a formal certificate and can place letters (to be determined) signifying that they are certified EAPs behind their name;

    •     An applicant can appeal to the High Court if his or her application is rejected by the Board;

    •     An EAP must re-apply to move up to the next category of certification; and

    •     Continuous Professional Development (CPD) and renewal every two years.

5.    Continuous Professional Development:

    Practitioners who have been registered should develop their personal attributes and skills by:

    •     Ensuring that their knowledge of environmental assessment techniques is current best practice;

    •     Ensuring that their knowledge of environmental laws, regulations and procedures is current;

    •     Undertaking refresher training where necessary; and

    •     Ensuring that their experience in the execution of relevant EA work is current and maintained.

    All registered individuals are required to keep a log of relevant experience and training, which must either be signed-off by their employer or client, or be substantiated by documentary proof.

    Log-sheets must be submitted to the Secretary of the Board on an annual basis at the time of renewal of registration or upon request. These will be assessed on a three yearly basis. Failure to demonstrate sufficient relevant EA work may result in the removal of the individual from the register.

    The aim of continuing professional development (CPD) is to ensure that EAPs are suitably informed of trends and developments in environmental assessment, including the legal requirements, policy objectives, EA procedures and tools. There should be a reporting interval of every two years, where certified EAPs will be required to submit a CPD report, setting out their achievements in terms of: conference attendance, presentation of papers, submission of papers to referred journals, seminar and workshop attendance and course completion.

    The appropriate type of CPD per EAP category and a working definition of CPD requirements per EAP category is outlined in the Table below. Note that the number of actions is based on a reporting interval of two years.

CPD Requirements to Maintain Registration as an EAP

(Trainee EAP is not required to maintain a CPD)

CPD element

EAP

Senior EAP

Principal EAP

Conferences

Attendance at a
minimum of one
conference in the
SADC region

Attendance at a
minimum of two
conferences in the
SADC region with
presentation of a paper
at one of these

Attendance at a
minimum of one
conferences in the
SADC region and one
international
conference (outside
SADC), with the
presentation of a paper
at two of these.

Courses

Attendance at a
minimum of two
EA- related
courses run by an
accredited
institution or
person

Attendance at a
minimum of one EA- related course run by an
accredited institution or
person

Presentation of a
minimum of one
accredited EA- related
course

Seminars and
lectures
workshops

Attendance at a
minimum of two
EA-related
seminars, lectures
or workshops

Attendance at a
minimum of two EA-related seminars,
lectures or workshops
and presentation of at
least one seminar,
lecture or workshop on
an EIA-related topic

Attendance at a
minimum of one EA-related seminar, lecture
or workshop and
presentation of at least
two seminars, lectures
or workshops on an
EIA-related topic

Published
Papers

N/A

A publication of at least
one paper in a non-referred
journal on an
EA-related topic

Publication of at least
one paper in a referred
journal on an EA-related
topic and one
paper in a non-referred
journal on an EA-related
topic

 

FORM C

(regs. 10(3) and 11)

FEE STRUCTURE

Registration Fees

 

Initial registration fee (P)

Citizen of Botswana

250

Resident of Botswana

500

Non-resident

1 000

 

Annual Subscriptions

 

Initial registration fee (P)

Citizen of Botswana

500

Resident of Botswana

1 000

Non-resident

1 500

 

Certification Fee

 

EAP

Senior EAP

Principal EAP

Citizen of Botswana

500

1 000

1 500

Resident of Botswana

1 000

1 500

2 000

Non-resident

1 500

2 000

2 500

 

Tariff of Professional Fees

Category of
Practitioner

Minimum daily rate (P)

Maximum daily rate (P)

EAP

1 600

2 600

Senior EAP

2 600

3 500

Principal EAP

3 500

5 000

 

FORM D

(reg. 11)

Certificate of Practice for Environmental Practitioners

 

 

(BACKSIDE OF CERTIFICATE)

The certification of the association has at present four levels, each with a certain level of competence and right to submit EIA documents to the Department of Environmental Affairs, as follows:

Education and experience required per category of certification

Proposed Category
of EAP

Tertiary qualification from a
recognised university in an
environmental discipline

Relevant working
experience in EIAs at
required level of competency
(see below)

Trainee EAP

Diploma, or Bachelors Degree, or
Graduate Degree

Little or no experience

EAP

Diploma, or
Bachelor’s Degree
or Masters Degree

3 years
2 years
1 years

Senior EAP

Diploma or
Bachelors Degree
or Masters Degree
or Doctorate Degree

5 years
4 years
3 years
2-3 years

Principal EAP

Diploma or
Bachelor degree
or Masters Degree
or Doctorate Degree

10 years
10 years
6 years
5 years

 

FORM E

(reg. 12)

Register of Environmental Practitioners

BEAPA REGISTER OF ENVIRONMENTAL ASSESSMENT PRACTITIONERS

BEPA
Serial
Number

Surname

First
Names

Title (Prof/
Dr/Mr/
Mrs/Ms

Sex
(Male/
Female)

Citizenship

Omang/
Passport
No.

Postal
Address

Physical
Address
(Residential)
Not
accessible to
the public
for security

Physical
Address
(Work)

Telephone,
Cellphone
& Fax
Numbers

E-mail
Address

Applicable
Tertiary
Qualification

Current
Certification
Level
(e.g.
Trainee
EAP, EAP,
SEAP
PEAP)

Membership
Status
(Active,
Suspended,
Disciplinary
Action
Expelled

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FORM F

(reg. 13(1))

CODE OF CONDUCT OF PRACTITIONERS REGISTERED UNDER THE ACT

Environmental Assessment Practitioners shall carry out their professional activities, as far as possible, in accordance with emerging principles of sustainable development, the highest standards of environmental conservation and quality, and in compliance with the letter and intent of relevant environmental legislation.

    i.    Environmental Assessment Practitioners shall at all times place the integrity of the environment, including conservation and sustainable use of the biophysical environment and the social welfare, health and safety aspects of the socio-economic environment, above any commitment to sectional or private interests.

    ii.    Environmental Assessment Practitioners shall ensure the incorporation of environmental considerations from the earliest stages of project conception or policy development.

    iii.    Environmental Assessment Practitioners shall not conduct professional activities in a manner involving dishonesty, fraud, deceit, misrepresentation or bias.

    iv.    Environmental Assessment Practitioners will clearly differentiate between facts and opinions in their work.

    v.    Environmental Assessment Practitioners will, to the best of their ability, keep informed of advances in environmental assessment practice, and will integrate such knowledge into their professional activities.

    vi.    Environmental Assessment Practitioners will inform a prospective client or employer of any professional or personal interests which may impair the objectivity of their work.

    vii.    Environmental Assessment Practitioners will not seek employment, grants or gain, or attempt to injure the reputation or opportunities for employment of another environmental assessment practitioner by false, biased or undocumented claims or accusations, by any other malicious action, or by offers of gifts or favours.

    viii.    Environmental Assessment Practitioners will, to the best of their ability, use the best available information.

    ix.    Environmental Assessment Practitioners should take responsibility for the findings of the environmental assessment. (However, the Environmental Assessment Practitioners cannot be held responsible for decisions made by other parties, purportedly based on the findings of the environmental assessment.)

    x.    Environmental Assessment Practitioners must only undertake particular environmental assessment work in a position of responsible charge where they have the relevant expertise and experience to undertake that work competently.

    xi.    Environmental Assessment Practitioners shall not advertise their professional services in a self-laudatory manner that may discredit the profession.

    xii.    Environmental assessment practitioners shall not misrepresent or allow or permit misrepresentation of their own or their associates’ academic or professional qualifications, or exaggerate their degree of responsibility for any work of a professional nature.

    xiii.    When requested to submit tender proposals, Environmental Assessment Practitioners shall structure any offer in such a way as to enable them to discharge their responsibilities to the client in every respect.

    xiv.    Environmental Assessment Practitioners shall not review for a particular client the work of another Environmental Assessment Practitioners except with the prior knowledge of such person and affording such person reasonable opportunity to submit comments on the findings of the review.

    xv.    Environmental Assessment Practitioners shall comply with the objectives of the Board as well as any bye-laws or rules laid down by such Board.

 

ENVIRONMENTAL ASSESSMENT (ESTABLISHMENT OF APPEALS COMMITTEE) ORDER

(section 13(2))

(19th March, 2019)

ARRANGEMENT OF PARAGRAPHS

    PARAGRAPH

PART I
Preliminary

    1.    Citation

PART II
Establishment of Appeals Committee

    2.    Establishment of Appeals Committee

    3.    Tenure of office of member

    4.    Filling of vacancy

    5.    Disqualification

    6.    Removal or suspension of member

    7.    Disclosure of interest

    8.    Confidentiality

    9.    Remuneration and allowances

PART III
Procedure of Appeals

    10.    Powers of Appeals Committee

    11.    Decision of Appeals Committee

    12.    Hearing to be open to public

    13.    Representation before Appeals Committee

    14.    Contempt of Appeals Committee

PART IV
Miscellaneous

    15.    Immunity from suit

S.I. 29, 2019.

PART I
Preliminary

1.    Citation

    This Order may be cited as the Environmental Assessment (Establishment of Appeals Committee) Order.

PART II
Establishment of Appeals Committee

2.    Establishment of Appeals Committee

    (1) There is hereby established a committee to be known as the Appeals Committee.

    (2) The Appeals Committee shall be composed of—

    (a)    a Chairperson; and

    (b)    two members appointed by the Minister who shall be from—

        (i)    any regulatory or licensing authority,

        (ii)    a non-governmental organisation,

        (iii)    the private sector,

        (iv)    any local authority, or

        (v)    registered and certified Environmental Assessment practitioners.

    (3) The Minister shall appoint the Chairperson of the Appeals Committee who—

    (a)    is an attorney admitted to practice in the courts of Botswana in accordance with the Legal Practitioners Act (Cap. 61:01); and

    (b)    has at least five years experience.

    (4) The Vice-Chairperson of the Appeals Committee shall be elected by the members from amongst their number.

    (5) The Appeals Committee shall meet at such place and time as it may determine and shall be convened by the Chairperson of the Appeals Committee.

    (6) The Chairperson shall preside at any meeting of the Appeals Committee and, in his or her absence, the Vice-Chairperson.

    (7) A decision of the Appeals Committee on any matter shall be by a majority of the members present and voting at the meeting and, in the event of an equality of votes, the Chairperson shall have a casting vote in addition to his or her deliberative vote.

    (8) At any meeting of the Appeals Committee, a quorum shall be constituted by at least two of the members.

3.    Tenure of office of member

    (1) The tenure of office of a member shall be for a period not exceeding five years or for such a period as may be stipulated in the instrument appointing him or her.

    (2) The appointment of members shall be staggered to ensure continuity of the business of the Appeals Committee.

    (3) A member whose term has expired shall be eligible for re-appointment for one more term.

4.    Filling of vacancy

    (1) Where the office of a member becomes vacant before the expiry of his or her term of office, the Minister shall, in accordance with paragraph 2, appoint another person to fill that vacancy and that appointment shall be for the remaining duration of the term of the original member.

    (2) The provisions of subparagraph (1) shall not apply where the remainder of the period for which the member who vacated office is less than six months.

5.    Disqualification

    A person shall not be appointed as a member, nor shall a person qualify to be appointed as a member who—

    (a)    is not a fit and proper person;

    (b)    has been adjudged or otherwise declared insolvent or bankrupt; or

    (c)    has been convicted of a criminal offence in or outside Botswana within the last ten years.

6.    Removal or suspension of member

    (1) The Minister may suspend a member where—

    (a)    that member is absent without reasonable cause from three consecutive meetings of the Appeals Committee; or

    (b)    criminal proceedings have been instituted against that member for an offence that attracts a prison sentence.

    (2) The Minister may remove a member where—

    (a)    that member is inefficient;

    (b)    a member is convicted of a criminal offence and sentenced to a prison term;

    (c)    a member has been found to be physically or mentally incapable of performing his or her duties efficiently; or

    (d)    a member has acted in contravention of the Environmental Assessment Act (Cap. 65:07).

7.    Disclosure of interest

    (1) Where a member is present at a meeting at which any matter which is the subject of consideration and in which matter that member is directly or indirectly interested in a private capacity, he or she shall forthwith, upon the commencement of the meeting, disclose such interest and shall not, unless the Appeals Committee otherwise directs, take part in any consideration or discussion of, or vote on, any question concerning that matter.

    (2) A disclosure of interest made under subparagraph (1) shall be recorded in the minutes of proceedings at which it is made.

    (3) Where a member fails to disclose his or her interest in accordance with subparagraph (1) and the Appeals Committee makes a decision which benefits that member directly or indirectly, that decision shall be void to the extent to which it benefits him or her.

    (4) A person who contravenes the provisions of subparagraph (1) commits an offence and is liable to a fine not exceeding P2 000, or to imprisonment for a term not exceeding three months, or to both.

8.    Confidentiality

    (1) A member shall not disclose any confidential information relating to the affairs of the Appeals Committee which he or she acquires during the performance of his or her duties in the Appeals Committee.

    (2) Notwithstanding the provisions of subparagraph (1), a member may disclose information relating to the affairs of the Appeals Committee acquired during the performance of his or her duties—

    (a)    within the scope of his or her duties; or

    (b)    where required to—

        (i)    by an order of court,

        (ii)    under any written law, or

        (iii)    in the investigation of an offence.

    (3) A person who contravenes the provisions of this paragraph commits an offence and is liable to a fine not exceeding P2 000 or to imprisonment for a term not exceeding three months, or to both.

9.    Remuneration and allowances

    A member shall be paid such remuneration, travelling expenses and other expenses and allowances, incurred in connection with his or her services in the Committee, if any, as the Minister may from time to time determine.

PART III
Procedure of Appeals

10.    Powers of Appeals Committee

    (1) The Appeals Committee shall in considering an appeal regulate its own proceedings and may—

    (a)    take evidence on oath;

    (b)    require a witness to produce relevant documents or to furnish written particulars as necessary; or

    (c)    adjourn any hearing and inform the parties of a date and time of the hearing.

    (2) The Appeals Committee shall hold its first meeting on such date and at such place as the Minister may determine, or as frequently as the business of the Appeals Committee demands that the Chairperson convenes the Appeals Committee, and at such a place and time as the Chairperson shall determine.

    (3) The Chairperson shall give notice of not less than 14 days written notice of the meeting, provided that if the urgency of any particular matter does not permit the giving of notice, a special meeting may be called by giving a shorter notice.

    (4) The Appeals Committee shall not be bound by the rules of evidence or procedure applicable in a court of law and may disregard any technical irregularity which is likely to result in a miscarriage of justice.

11.    Decision of Appeals Committee

    (1) The Appeals Committee may—

    (a)    affirm the decision of the competent authority; or

    (b)    vary or set aside the decision of the competent authority and remit the matter to the competent authority for consideration in accordance with its direction or recommendation.

    (2) The Appeals Committee shall give reasons in the form of a written decision signed by the Chairperson and such decision shall be served on the parties.

    (3) Subject to subparagraph (5), a decision of the Appeals Committee shall come into operation upon the giving of the decision or on such other date as may be specified by the Appeals Committee.

    (4) Where the Appeals Committee varies a decision of the competent authority, the decision as varied shall be deemed to be the decision of the competent authority unless the Appeals Committee orders otherwise.

    (5) A decision of the Appeals Committee shall have effect and be enforceable as if it were a decision of a court of competent jurisdiction.

    (6) A decision of the Appeals Committee shall be a public record and shall be open to inspection by any member of the public during office hours.

12.    Hearing to be open to public

    A hearing before the Appeals Committee shall be open to the public unless the Appeals Committee, on the request of either party, directs otherwise.

13.    Representation before Appeals Committee

    A party to the proceedings before the Appeals Committee may be represented by a legal practitioner, or be represented by any other person so authorised by the party.

14.    Contempt of Appeals Committee

    A person who—

    (a)    interrupts the proceedings of the Appeals Committee;

    (b)    disregards the decision of the Appeals Committee; or

    (c)    does anything that would, if the Appeals Committee were a court of record, constitutes contempt of court,

commits an offence and is liable to a fine not exceeding P5 000 or to imprisonment for a term not exceeding six months, or to both.

PART IV
Miscellaneous

15.    Immunity from suit

    A person shall not bring any action, suit, prosecution or any other proceeding personally against a person who is or was a member of the Appeals Committee in respect of any act done or omitted to be done in good faith in the discharge of any function under this Order.


Scroll to Top